The River Ash is a chalk stream tributary which had become heavily degraded due to abstraction, impoundments, over-shading, and invasive species. Historic modifications restricted natural flows, prevented fish passage, and left the river corridor disconnected from its floodplain. Steep, unstable banks further reduced resilience during high flows and limited safe access for both people and wildlife.
In 2024, R.J. Bull Limited were contracted to restore 7 km of river corridor across Reaches 4 (lower), 6 and 7. Working closely with Hertfordshire and Middlesex Wildlife Trust, our objective was to improve the river’s hydro-morphological condition, reconnect habitats, increase flood resilience, and create a mosaic of diverse habitats that would support fish, invertebrates, macrophytes, and riparian wildlife.
What did we do?
We began with extensive regrading of the riverbanks, improving both accessibility and resilience to high flows. A major reinforced concrete weir was removed, restoring natural flows, exposing gravel riffles, and reconnecting fragmented habitats. Using site-won gravels, woody material, and brash, we created a range of new in-channel features designed to increase habitat diversity and encourage natural fluvial processes.
To improve light penetration, selective coppicing and scrub clearance were carried out across heavily shaded sections. Alongside this, we formed new lateral habitats including ponds, scrapes, wetlands, wet woodland, and backwaters, creating a mosaic of features across the floodplain. Timber structures were installed and securely pinned with chestnut posts and wire for long-term stability. Finally, all regraded banks and new features were seeded and planted with native mixes and plug plants, ensuring rapid establishment of sustainable riparian vegetation.
The challenges?
- Public access – works were phased to ensure visitor safety throughout
- Protected species – adaptive working around water vole activity, avoiding active burrows
- Access restrictions – limited machinery access required sequential working and maximum reuse of site-won material
- Large weir structure – phased removal and careful reprofiling of exposed riffles
- Overhead power lines – required specific health & safety measures and restrictions on machinery use
- Invasive species – biosecurity measures and targeted removal of Himalayan Balsam and Signal Crayfish
What were the results?
The completed works transformed seven kilometres of chalk stream corridor. More than 6,000 m³ of material was reprofiled to create inset floodplains, scrapes, wetlands, backwaters, and new ponds, significantly diversifying the range of habitats available. Removal of the weir and placement of gravel riffles restored fish passage, while the creation of woody features enhanced morphology and provided vital refuges for aquatic species.
By carefully managing shading, light levels were increased, encouraging in-channel vegetation recovery and supporting a richer ecological community. Flood resilience was also improved through the reconnection of the river to its natural floodplain. Crucially, public access was maintained throughout the project, allowing visitors to continue enjoying the river while its long-term ecological and hydrological function was improved. Overall, the project not only met but exceeded its objectives, delivering substantial biodiversity uplift and greater connectivity across the river corridor.